Willamette River Crossing Project

Project overview

To accommodate the U.S. Environmental Protection Agency’s (EPA) long planned cleanup of the Portland Harbor Superfund Site, we plan to remove the existing power supply cables in the sediment of the Willamette River in Portland located between the Broadway and Fremont Bridges. To preserve power service and reliability to our customers, we will replace the old lines with a new group of lines. The new underground line will be approximately 2 miles long and will be located underneath the bed of the river. The new underground line will be placed inside a two, 2-foot diameter, 3,000-foot-long tunnels to be drilled under the riverbed. The new lines will be installed and placed into service in advance of any existing line removal or EPA cleanup.

Background

The eastern portion of the existing Centennial Mills Cable Crossing power line is located in an area where sediments containing polychlorinated biphenyls (PCBs) and other contaminants are present. The EPA has identified this area for remediation as part of the River Mile 11 East (RM11E) Portland Harbor Superfund Site Project. In their January 2017 Record of Decision for Portland Harbor, EPA recommended that the area be dredged and/or capped. Unfortunately, neither one of these alternatives are feasible if the Centennial Mills Cable Crossing remains in place. To accommodate the requirements to remediate the RM11E Area in the Portland Harbor Superfund Site Record of Decision, and as directed by EPA in its comments on the RM11E Implementability Study Report, Pacific Power (A Division of PacifiCorp) has explored the feasibility of relocating the submarine cable crossing to allow sediments in proximity to the existing crossing to be dredged and/or capped. Pacific Power has identified the Willamette Crossing Project as the preferred alternative for providing uninterrupted electric service to the Albina network so that the Centennial Mills Cable Crossing can be removed from service as part of the RM11E remediation activities. Learn more about the Portland Harbor Superfund Site.

Frequently Asked Questions

Frequently Asked Questions

Project update

Currently the project team is working on the detailed design and final permitting. The Horizontal Direction Drill (river crossing route) and the eastern and western onshore routes have been identified and final approvals are in process. Construction is currently underway in The Fields Park, along N. Dixon Street and other streets. 

  • Week of April 21
    • Fields Park – Sound wall removal and open trench set up
    • N. Dixon Street – Demobilization and restoration
    • East side of river city streets – Vault work and excavation, including some closures, on N Lewis, N Page and N Kerby
    • West side of river city streets – Set up for trenching and excavation at NW 11th Ave. and NW Pettygrove
  • Week of April 28
    • Fields Park – Transition to open trench construction
    • N. Dixon Street – No work
    • East side of river city streets – Splicing and electrical installation in vaults and railroad crossing installation, traffic control and partial closures on N Lewis, N Wheeler and N Thompson
    • West side of river city streets – No work
  • Week of May 5
    • Fields Park – No work, open trench pending work on NW Pettygrove
    • N. Dixon Street – No work
    • East side of river city streets –  Splicing and electrical installation in vaults and railroad crossing installation, traffic control and partial closures on N Lewis, N Wheeler and N Thompson
    • West side of river city streets – Excavation at NW 11th Ave. and NW Pettygrove
  • Week of May 12
    • Fields Park – No work, open trench pending work on NW Pettygrove
    • N. Dixon Street – No work
    • East side of river city streets –  Splicing and electrical installation in vaults and railroad crossing installation, traffic control and partial closures on N Lewis, N Wheeler, N Thompson and N Page
    • West side of river city streets – Excavation at NW 11th Ave. and NW Pettygrove
  • Week of May 19
    • Fields Park – Open trenching
    • N. Dixon Street – No work
    • East side of river city streets –  Splicing and electrical installation in vaults and railroad crossing installation, traffic control and partial closures on N Lewis, N River, N Albina and N Page
    • West side of river city streets – Excavation at NW 11th Ave. and NW Pettygrove

Project timeline

Design, permitting & Right of Way – 2019 - 2024

Engineering & Equipment Procurement – 2022 - 2023

Construction

  • Construction begins – Q4 2023
  • River Crossing Underground Crossing – 2023 - 2025
    • Including partial closure of The Fields Park
  • Onshore West Side Construction – 2023 - 2026
  • Onshore East Side Construction – 2023 - 2025
  • Completion – Late 2026

Map 

Project contact

Email PacificPowerConstruction@PacifiCorp.com and include the project name “River Crossing” in your inquiry.  
Or, call 1-888-221-7070.