This site uses cookies and related technologies to enhance user experience, analyze performance and traffic on our website, and to enable our service providers to provide you with targeted communications. For details on how we use cookies and the personal information we collect, review our Privacy Policy.
We are committed to developing partnerships with large customers to foster beneficial growth in the communities we serve.
These relationships are essential in developing sustainable, reliable power solutions that keep pace with evolving industry demands.
        
    
    
This is a request for new or expanded electric service for a large energy user.
In Oregon, the unique threshold is:
If your load request is less than 20 MW, please visit our Builders & Contractors web pages or call our customer service team at 1-888-221-7070.
The customer should contact us at Largeloads@PacifiCorp.com to receive the Customer Information Form and Financial Information Requirements. These complete documents need to be submitted to us through email. We'll let you know if there's any incomplete information.
Pacific Power accepts requests for large service on a continual basis in Oregon.
After completing the initial system impact study, Pacific Power (a division of PacifiCorp) will provide the customer with a written service proposal that will include:
A large-scale service request must include:
Email us at Largeloads@PacifiCorp.com for copies of the forms.
Pacific Power strives to complete an evaluation in no more than six months after the submittals and study payment have been received. This timeline can be impacted by necessary customer submittals or integration with other large load requests on the system.
The evaluation cost for a large-scale service request will be a minimum of $150,000, payable upon execution of an Engineering Service Agreement.
Service agreements for Computing Infrastructure Providers, Data Processing, Web Hosting, and Related Services over 20 MW in Oregon will require a special contract which requires commission approval. Service agreements for non-computing over 20 MW may require a large load contract with commission approval.
A large customer will pay all reasonable incremental costs necessary to provide electric service which may include, depending on project scope:
Also, to the extent permitted by the Federal Energy Regulatory Commission (FERC), the contract will include:
This is a request for new or expanded electric service for a large energy user.
In Washington, the unique threshold is:
If your load request is less than 20 MW, please visit our Builders & Contractors web pages or call our customer service team at 1-888-221-7070.
The customer should contact us at Largeloads@PacifiCorp.com to receive the Customer Information Form and Financial Information Requirements. These complete documents need to be submitted to us through email. We'll let you know if there's any incomplete information.
Pacific Power accepts requests for large service on a continual basis in Washington.
After completing the initial system impact study, Pacific Power (a division of PacifiCorp) will provide the customer with a written service proposal that will include:
A large-scale service request must include:
Email us at Largeloads@PacifiCorp.com for copies of the forms.
Pacific Power strives to complete an evaluation in no more than six months after the submittals and study payment have been received. This timeline can be impacted by necessary customer submittals or integration with other large load requests on the system.
The evaluation cost for a large-scale service request will be a minimum of $150,000, payable upon execution of an Engineering Service Agreement.
Service agreements over 20 MW in Washington may require a special contract which requires commission approval.
A large customer will pay all reasonable incremental costs necessary to provide electric service which may include, depending on project scope:
Also, to the extent permitted by the Federal Energy Regulatory Commission (FERC), the contract will include:
This is a request for new or expanded electric service for a large energy user.
In California, the unique threshold is:
If your load request is less than 20 MW, please visit our Builders & Contractors web pages or call our customer service team at 1-888-221-7070.
The customer should contact us at Largeloads@PacifiCorp.com to receive the Customer Information Form and Financial Information Requirements. These complete documents need to be submitted to us through email. We'll let you know if there's any incomplete information.
Pacific Power accepts requests for large service on a continual basis in Oregon.
After completing the initial system impact study, Pacific Power (a division of PacifiCorp) will provide the customer with a written service proposal that will include:
A large-scale service request must include:
Email us at Largeloads@PacifiCorp.com for copies of the forms.
Pacific Power strives to complete an evaluation in no more than six months after the submittals and study payment have been received. This timeline can be impacted by necessary customer submittals or integration with other large load requests on the system.
The evaluation cost for a large-scale service request will be a minimum of $150,000, payable upon execution of an Engineering Service Agreement.
Service agreements over 20 MW in California will require a special contract which requires commission approval.
A large customer will pay all reasonable incremental costs necessary to provide electric service which may include, depending on project scope:
Also, to the extent permitted by the Federal Energy Regulatory Commission (FERC), the contract will include: